Sheet piling and piling works
As part of the climate adaptation of the city of Kolding, a new pumping and sluice facility was constructed at the outlet of the Kolding Å to protect the city against flooding during storm surge events.
The challenging ground conditions, with soft soils extending to significant depths, required extensive sheet piling and piling works to provide a stable foundation for the sluice structure. The sheet piles were installed using a free-hanging vibratory hammer suspended from a crane. The piles in Kolding Å were driven from a temporary working platform established on the driven piles.
Main quantities
-
7,600 m² of permanent sheet pile walls in lengths of 18–28 metres
-
450 driven 300 × 300 mm piles in lengths of 20–25 metres, including trimming
-
40 tonnes of internal bracing in the excavation
-
Temporary piled working platform for pile driving
-
PDA / CAPWAP testing of driven piles
Project facts
- Contract type: Trade contract
- Client: Jorton A/S
- Execution period: May 2024 – November 2025
- Contract sum: Not disclosed